Project title : Construction of Double – Truck of Qom Railway And It’s Interchange
Client: Islamic Republic of Iran Railway
Consultant : Hexa Consultants
Contractor : Nasran – Haraz Rah Consulting Engineers Group Cooperation
Location : Qom
Start Date : Jul 2015
Finish Date : In Progress
Project subject: Construction of Double – Truck of Qom Railway And It’s Interchange

| Row No | Name | Unit | Quantity |
|---|---|---|---|
| 1 | Reinforcement | Ton | 4,000 |
| 2 | Concrete | m3 | 42,000 |
| 3 | Pile drilling | ML | 20,000 |
| 4 | Pre-Cast Concrete | m3 | 3,500 |
| 5 | Metal Works | Ton | 370 |
| 6 | Formwork | m2 | 19,000 |
| 7 | Earthworks | m3 | 160,000 |







