Project title : Delijan 3300 Ton /Day Cement Factory
Client: Omran Anarak Cement Factory
Consultant: Dahe Consultants
Location : Salafchegan – Delijan
Start Date : Feb 2005
Finish Date : Jun 2008
Project subject: Civil construction of Cement Factory Contains Steel & Concrete Structure of Crusher, Raw Mill, Raw Feed, Raw Storage, Preheater, Cooling Tower, Fans, Kilns, Main Control, Compressor Room, Substances and Landscaping

| Row No | Name | Unit | Quantity |
|---|---|---|---|
| 1 | Earthworks | m3 | 138,000 |
| 2 | Slipforms | m3 | 11,000 |
| 3 | Reinforcement | Ton | 4,500 |
| 4 | Concrete | m3 | 37,000 |
| 5 | Steel structure | Ton | 2,200 |
| 6 | Formwork | m3 | 64,000 |
| 7 | Architectural work | m2 | 3,500 |
| 8 | Landscaping | m2 | 15,000 |