Client: Makran Chabahar Steel Company
Consultant: Fooladtechnic International Consultant Engineers
Contractor: Nasran Co.
Project subject: Construction of structures and road construction of Makran Steel Reduction Department
Location: Chabahar
Start Date: Sep 2021
Current Status: In progress
Description of works: Construction of structures and road construction project of Makran Steel Factory Reduction Department, Including construction of industrial structures of the plant, power canals and office building and infrastructure system.
Row | Description | Unit | Quantity |
---|---|---|---|
1 | Formwork | m2 | 41,000 |
2 | Reinforcement | ton | 2,630 |
3 | Concreting | m3 | 28,000 |
4 | Pile Drilling | ml | 1,000 |